SL.NO DESCRIPTION OF WORK TYPE OF WORK COMPLETED DATE ON
1 Construction for Road Under Bridge RUB at Km.0/6 of Nanganallur road in lieu of exg. Level crossing near Palavanthangal Railway Station. ROAD UNDER BRIDGE(RUB) May 1997
2 Improvements to Radial roads in and around Chennai City -Package No.4 – Two lanning & Strengthening of Vandalore – Walajabad road Km.30/4 to 63/8 and Providing hard shoulders to Tambaram – Mudichur road – Km.0/0 to 7/4 including culverts & Bridges. ASPHALT ROAD WORK March 2001
3 Construction of ROB at Km 0/10 of Omalur Sankari Road near Omalur Railway Station, Salem ROAD OVER BRIDGE (ROB) January 2005
4 Re – Construction of High Level Bridge across Manimuktha river at Km.53/10 – 54/20 of Cuddalore – Vridhachalam – Salem Road. HIGH LEVEL BRIDGE (HLB) March 2007
5 “Short Term Improvement of Thiruvottiyur- Ponneri- Panchetti road from Km 4/500 to 13/500 in the Chennai – Ennore Port road Connectivity Project in the state of TamilNadu” ASPHALT ROAD WORK April 2009
6 Construction of High Level Bridge across Adhambakkam lake at KM 1/400-1/750 of Southern sector of inner Ring road from KM.14/1 of NH 45 to meet at KM.13/4 of Chennai – Old Mahabalipuram Road (Rajiv Gandhi Road) in Chennai City HIGH LEVEL BRIDGE (HLB) February 2011
7 Widening to two lane and Strengthening of Singaperumal koil – reddykuppam road km 4/5 – 9/0 ASPHALT ROAD December 2012
8 The work of “Construction of Road Over Bridge in lieu of L C. No. 36, Railway Km 36/12 -14 in between Vandalur and Guduvanchery railway stations near Urappakkam.(Foreclosed the contract due to Land acquisition problem) ROAD OVER BRIDGE (ROB) December 2013
9 The work of “Construction of road over bridge in lieu of L C. No. 14, in between Thirunindravur and Thiruvallur railway stations near Veppampattu railway station. (Foreclosed the contract due to Land acquisition problem) ROAD OVER BRIDGE (ROB) March 2013
10 Construction of ROB in lieu of existing LC No 5 Railway km 13/4-6 in between Ambattur and Villivakkam Railway Stations at Pattravakkam ROAD OVER BRIDGE (ROB) March 2014
11 Package 10, Junction Improvements, Strengthening, and Improvements works in Chengalpattu (H), C & M Sub Division jurisdiction ASPHALT ROAD December 2017