SI.NO DESCRIPTION OF WORK TYPE OF WORK COMPLETED DATE ON
1 Widening of exg. Napier bridge across Cooum river in Kamarajar Salai Division.80, Chennai City NAPIER BRIDGE July 1999
2 Construction of High Level bridge in lieu of exg. Cause way across Cooum river in Naduvankarai – Chennai City HIGH LEVEL BRIDGE (HLB) April 2001
3 Construction of Vehicular Subway in lieu of existing level Crossing at Harrington Road in DN-72&78, Zone-V” – Chennai City. ROAD UNDER BRIDGE (RUB) July 2006
4 Package – 2 (31 Roads) Forming and Laying BT Road at Various street in Dn. 168,169,185 & 188 ASPHALT ROAD December 2012
5 Package – 1 (25 Roads) Forming and Laying BT Road at Various street in Dn. 183, 185 ASPHALT ROAD January 2013
6 Package – 3 (30 Roads) Forming and Laying BT Road at Various street in Dn. 189,190 & 191 ASPHALT ROAD February 2013
7 Integrated road development” including roads ,Street Lights and Street furniture at various Roads in extended areas in Zone – XIV (Package-3 A) ( 14 Roads) ASPHALT ROAD March 2013
8 Integrated road development including storm water drain, ducts for cables, Street Lights and Street furniture’s at various Roads in extended areas in Zone VII –Package – 1 (14 roads)”. ASPHALT ROAD AND DRAIN March 2013
9 Zone XIV– “Chennai Mega City Development Mission (PHASE -2)” Integrated road development including storm water drain, ducts for cables, Street Lights and Street furnitures at various Roads in Ward 189, in Zone – XIV – Package 2 – (11 roads)”@ Corporation of Chennai ASPHALT ROAD AND DRAIN November 2013
10 Zone XIV– “Chennai Mega City Development Mission (PHASE -2)” – Integrated road development including storm water drain, ducts for cables, Street Lights and Street furnitures at various Roads in Ward -191, in Zone – XIV – package 3 – (5 roads)” @ Corporation of Chennai ASPHALT ROAD AND DRAIN November 2013
11 Zone XIV– “Chennai Mega City Development Mission (PHASE -2)” – Integrated road development including storm water drain, ducts for cables, Street Lights and Street furnitures at various Roads in Ward – 187 & 189, in Zone – XIV – Package 5 – (23 roads)” @ Corporation of Chennai ASPHALT ROAD AND DRAIN December 2013
12 Zone- XII / C.No.E1/5077/2012 /Dated.03.05.2013 – Package- 2A- (21 Road works) Integrated road development including ducts for cables, Street lights and Street furniture at various Roads in Ward – 164&165 Zone XII under Chennai Megacity Development Mission Fund ASPHALT ROAD January 2014
13 Zone VII– “Chennai Mega City Development Mission (PHASE -2)” – Integrated road development including storm water drain, ducts for cables, Street Lights and Street furnitures at various Roads in Ward – 79,81 & 82, in Zone – VII– Package 1 – (8 roads)” @ Corporation of Chennai ASPHALT ROAD AND DRAIN February 2014
14 Package-2(19 Road works &14 Footpath works ) Relaying with CBC 40mm thick by Paver Finisher after Cold Milling to a depth of 40mm at various roads in Zones-IX and improvements to Footpath using granite Kerb and Slab at various roads in Zone- IX for the year 2012- 13@ Corporation of Chennai dated 15.02.2013” ASPHALT ROAD AND FOOTPATH March 2014
15 Package-2 ( 46 Road works) Integrated road development including Storm water drain, ducts for cables, Street Lights and Street furniture at various Roads in ward no185, 186 &187 Zone XIV under Chennai Megacity Development Mission ASPHALT ROAD AND DRAIN October 2014
16 Package-3 ( 41 Road works) Integrated road development including Storm water drain, ducts for cables, Street Lights and Street furniture at various Roads in ward no168,169 ,187 & 188 Zone XIV under Chennai Megacity Development Mission Fund ASPHALT ROAD AND DRAIN October 2014
17 Package- 1 – (118 Roads ) Integrated Road work at Various roads in Dn-192, Zone-XV Under Chennai Megacity Development Mission 1 Savings Fund”@ Corporation of Chennai ASPHALT ROAD April 2014
18 10000 roads (PACKAGE- 30): 39 Road works Forming, strengthening and laying the road at Various Street in Dn -189, Unit- 43, Zone- XIV ASPHALT ROAD February 2015
19 10000 roads Package-39 (41 Road Works) Forming, strengthing and laying the road at various Roads in Dn -190, Unit- 43, Zone- XIV ASPHALT ROAD February 2015
20 Z.O.VII.C.NO:E1/23818/07/2013 10000 roads Package No: 07 ( 23 Roads) Forming and Laying the BT Road by Paver Finisher at Various Streets in Division -82,Zone-VII ASPHALT ROAD August 2015
21 Z.O.VII.C.NO:E1/23818/06/2013 10000 roads Package No: 06 ( 22 Roads) Forming and Laying the BT Road by Paver Finisher at Various Streets in Division -82, Zone-VII ASPHALT ROAD August 2015
22 Z.O.VII.C.NO:E1/23818/13/2013 10000 roads Package No:13 ( 8 Roads) Forming and Laying the BT Road by Paver Finisher at Various Streets in Division – 83, Zone-VII ASPHALT ROAD August 2015
23 Z.O.VII.C.NO.E1/21053 /2013 Package-2 (81 Road works) Integrated road development including Storm water drain, ducts for cables, Street Lights and Street furniture at various Roads in ward no 81 & 82 Zone VII under Chennai Megacity Development Mission Fund ASPHALT ROAD AND DRAIN January 2016
24 BRR.C.No.B1/362/2015 Package 24 Strengthening and Relaying the Road with DBM and CBC after cold milling by Paver Finisher using Plastic waste along with Traffic Improvement work at 9 Bus Route Roads in Zone- 5,7 and 8 ASPHALT ROAD WITH MILLING January 2016
25 BRR.C.No.B1/360/2015 Package 22 Strengthening and Relaying the Road with DBM and CBC after cold milling by Paver Finisher using Plastic waste along with Traffic Improvement work at 4 Bus Route Roads in Zone – 1 ASPHALT ROAD WITH MILLING March 2016
26 Improvement to 75 Nos of interior roads in Dn 192 to 196, Zone -15 Package 3 ASPHALT ROAD WITH MILLING September 2016
27 Improvements to the interior B.T road in Zone 14 Package – 29(15 roads) ASPHALT ROAD WITH MILLING April 2017
28 Package – 7 Attending to Temporary Restoration of Damaged roads due to Flood in North East Monsoon 2015 at 12 Bus Route Roads in Zone- 8,9,10 ASPHALT ROAD WITH MILLING March 2017
29 Package – 27 Improvements to the Interior Roads in Zone-XV,(19 Roads), ASPHALT ROAD WITH MILLING March 2017
30 Providing and laying Cement concrete roads at 23 Nos of interior roads Zone 13, Package – 19 Concrete road August 2017
31 Improvements to the Marina Loop road by Laying cement concrete road, forming cycle track , Paving with granite footpath with railing of stainless steel pipe and Granite Pedestal stone along with Construction of SWD, Construction for RCC duct for service utilities and construction of underground drainage system etc from junction of Kamarajar salai towards Pattinampakkam in division -125, zone IX, Ch 850 m to 1800m Cement Concrete road, SWD, Footpath and RCC duct March 2018
32 Package – 19 Improvements to the Interior BT Roads in Zone-VIII, DN-101,103,104,105 & 106 (52 Roads) ASPHALT ROAD August 2018