SOUTHERN RAILWAY

SL.NO DESCRIPTION OF WORK VALUE IN LAKSH COMPLETED ON
1 Construction of ROB Stage III Pile Foundation etc., MTP Railway at Velachery Station, Chennai (Steel and cement department supply) 221 Feb. 2005
2 MRTS-Phase-1-Chennai Beach-Tirumailai-Construction of Retaining wall along road side of Buckingham canal at mundakanniamman Koil Station Building 685.85 Sep-11

HIGHWAYS DEPARTMENTS

SL.NO DESCRIPTION OF WORK VALUE IN LAKSH COMPLETED ON
1 Construction for Road Under Bridge RUB at Km.0/6 of Nanganallur road in lieu of exg. Level crossing near Palavanthangal Railway Station. 282.24 May-97
2 Improvements to Radial roads in and around Chennai City -Package No.4 – Two lanning & Strengthening of Vandalore – Walajabad road Km.30/4 to 63/8 and Providing hard shoulders to Tambaram – Mudichur road – Km.0/0 to 7/4 including culverts & Bridges. 1517.62 Mar-01
3 Construction of ROB at Km 0/10 of Omalur Sankari Road near Omalur Railway Station, Salem 566.97 Jan.2005
4 Re – Construction of High Level Bridge across Manimuktha river at Km.53/10 – 54/20 of Cuddalore – Vridhachalam – Salem Road. 546.72 Mar.2007
5 Construction of High Level Bridge across Adhambakkam lake at KM 1/400-1/750 of Southern sector of inner Ring road from KM.14/1 of NH 45 to meet at KM.13/4 of Chennai – Old Mahabalipuram Road (Rajiv Gandhi Road) in Chennai City 1227.31 Feb. 2011
6 Widening to two lane and Strengthening of Singaperumal koil – reddykuppam road km 4/5 – 9/0 295.77 Dec-12
7 The work of “Construction of Road Over Bridge in lieu of L C. No. 36, Railway Km 36/12 -14 in between Vandalur and Guduvanchery railway stations near Urappakkam.(Foreclosed the contract due to Land acquisition problem 612.61 Dec-13
8 The work of “Construction of road over bridge in lieu of L C. No. 14, in between Thirunindravur and Thiruvallur railway stations near Veppampattu railway station. (Foreclosed the contract due to Land acquisition problem 641.19 Mar-13
9 Construction of ROB in lieu of existing LC No 5 Railway km 13/4-6 in between Ambattur and Villivakkam Railway Stations at Pattravakkam 1671.45 Mar-14

CORPORATION OF CHENNAI

SL.NO DESCRIPTION OF WORK VALUE IN LAKSH COMPLETED ON
1 Widening of exg. Napier bridge across Cooum river in Kamarajar Salai Division.80, Chennai City 411 Jul-99
2 Construction of High Level bridge in lieu of exg. Cause way across Cooum river in Naduvankarai – Chennai City 325.66 Apr-01
3 Construction of Vehicular Subway in lieu of existing level Crossing at Harrington Road in DN-72&78, Zone-V” – Chennai City. 322.81 July 2006.
4 Package – 2 (31 Roads) Forming and Laying BT Road at Various street in Dn. 168,169,185 & 188 225.55 Dec-12
5 Package – 1 (25 Roads) Forming and Laying BT Road at Various street in Dn. 183, 185 275.35 Jan-13
6 Package – 3 (30 Roads) Forming and Laying BT Road at Various street in Dn. 189,190 & 191 252.13 Feb-13
7 Integrated road development” including roads ,Street Lights and Street furniture at various Roads in extended areas in Zone – XIV (Package-3 A) ( 14 Roads) 631.84 Mar-13
8 Integrated road development including storm water drain, ducts for cables, Street Lights and Street furniture’s at various Roads in extended areas in Zone VII –Package – 1 (14 roads)”. 1100.71 Mar-13
9 Zone XIV– “Chennai Mega City Development Mission (PHASE -2)” Integrated road development including storm water drain, ducts for cables, Street Lights and Street furnitures at various Roads in Ward 189, in Zone – XIV – Package 2 – (11 roads)”@ Corporation of Chennai 487.37 Nov-13
10 Zone XIV– “Chennai Mega City Development Mission (PHASE -2)” – Integrated road development including storm water drain, ducts for cables, Street Lights and Street furnitures at various Roads in Ward -191, in Zone – XIV – package 3 – (5 roads)” @ Corporation of Chennai 460.99 Nov-13
11 Zone XIV– “Chennai Mega City Development Mission (PHASE -2)” – Integrated road development including storm water drain, ducts for cables, Street Lights and Street furnitures at various Roads in Ward – 187 & 189, in Zone – XIV – Package 5 – (23 roads)” @ Corporation of Chennai 909.58 Dec-13
12 Zone- XII / C.No.E1/5077/2012 /Dated.03.05.2013 – Package- 2A- (21 Road works) Integrated road development including ducts for cables, Street lights and Street furniture at various Roads in Ward – 164&165 Zone XII under Chennai Megacity Development Mission Fund 391.68 Jan-14
13 Zone VII– “Chennai Mega City Development Mission (PHASE -2)” – Integrated road development including storm water drain, ducts for cables, Street Lights and Street furnitures at various Roads in Ward – 79,81 & 82, in Zone – VII– Package 1 – (8 roads)” @ Corporation of Chennai 842.51 Feb-14
14 Package-2(19 Road works &14 Footpath works ) Relaying with CBC 40mm thick by Paver Finisher after Cold Milling to a depth of 40mm at various roads in Zones-IX and improvements to Footpath using granite Kerb and Slab at various roads in Zone- IX for the year 2012- 13@ Corporation of Chennai dated 15.02.2013” 1029.59 Mar-14
15 Package-2 ( 46 Road works) Integrated road development including Storm water drain, ducts for cables, Street Lights and Street furniture at various Roads in ward no185, 186 &187 Zone XIV under Chennai Megacity Development Mission 2047.75 Oct-14
16 Package-3 ( 41 Road works) Integrated road development including Storm water drain, ducts for cables, Street Lights and Street furniture at various Roads in ward no168,169 ,187 & 188 Zone XIV under Chennai Megacity Development Mission Fund 2047.75 Oct-14

AIRPORTS AUTHORITY OF INDIA

SL.NO DESCRIPTION OF WORK VALUE IN LAKSH COMPLETED ON
1 Re – Construction of Taxiway ‘J’ from Junction of Runway – 30 to Runway – 25 at Chennai Airport 255.34 Jun.2007
2 Construction of RCC Box Drains behind Bay No. 9 & 10 at Chennai Airport, Chennai 148.36 Aug. 2008
3 Re – construction of bays No.9 & 10 for parking of wide bodied aircrafts at Chennai Airport, Chennai 517.17 Dec. 2008
4 Construction of Security Compound Wall @ Runway – 12 for providing 150m Strip at Chennai Airport, Chennai (Phase – II). 373.87 Feb. 2009
5 Re – Construction Of Bay No 27 at Chennai Airport, Chennai 220.74 Dec-09
6 “Re – Construction of Bay No.8 including construction of RCC Box drain across the Proposed Area at Chennai Airport, Chennai 308.14 Jan . 2010
7 Construction of Perimeter wall for encompassing AAI land at North of Runway 07 at Chennai Airport, Chennai 495.1 Nov. 2010
8 Construction of Angular taxi track (F1) connecting main runway 07-25 and B taxi track at Chennai Airport Chennai”. 889.39 Feb. 2013

INDIAN INSTITUTE OF TECHNOLOGY

SL.NO DESCRIPTION OF WORK VALUE IN LAKSH COMPLETED ON
1 “Re- Carpeting of major roads at IIT Madras Campus”, Chennai–600 036 281 Jun-09
2 Re-carpeting minor roads at IITM and constructing new roads at various locations on minor roads at IITM Campus 457.41 Jun-15

CHENNAI PORT TRUST

SL.NO DESCRIPTION OF WORK VALUE IN LAKSH COMPLETED ON
1 Providing Water Bound Macadam Road from South Tower of Old Entrance to Hazardous cargo shed 129.5 Jun-08

CMDA (CHENNAI METROPOLITAN DEVELOPMENT AUTHORITY)

SL.NO DESCRIPTION OF WORK VALUE IN LAKSH COMPLETED ON
1 Providing Gravel filling, Cement Concrete pavement, Storm Water Drain Culvert etc. for Proposed Lorry Parking Yard in about 7.62 acres in S.No.173/2pt, 198/1&2pt and 201/1&2 of Koyambedu village, Koyambedu, Chennai – 92 (AREA = 24800 SQM) 503.17 Jan-11
2 Relaying of CC Road (M30) and Providing R.C.C. Storm Water Drain in Truck bays ‘H to N’ Blocks of Vegetable Market at Koyambedu Wholesale Market Complex, Koyambedu, Chennai – 92 168.16 Dec-12
3 Relaying of CC Road (M30) and Prov R.C.C. Storm Water Drain from Gate No.7 to 14 and Part of ‘A’ Road at Koyambedu Wholesale Market Complex, Koyambedu – 92 208.54 Dec-12
4 Widening and Strengthening of part of ‘E’ road at Koyambedu Wholesale Market Complex, Koyambedu, Chennai- 92 220.22 Feb-13
5 Providing and Relaying of RMC (M30) Road and RCC SWD for North and West side of Flower Market @ KWMC, Koyambedu 170.3 Dec-13

TAMIL NADU HOUSING BOARD

SL.NO DESCRIPTION OF WORK VALUE IN LAKSH COMPLETED ON
1 Providing gravel soling and WBM to on site roads in Phase.I area at Ambattur Site & Service Ambattur. 136.1 Jun-96
2 Providing gravel soling and WBM to on site roads in Phase.II area at Ambattur Site & Service Ambattur. 201.88 Dec-95

SICAL DISTRIPARKS LIMITED, CHENNAI AND TUTICORIN (PRIVATE WORKS)

SL.NO DESCRIPTION OF WORK VALUE IN LAKSH COMPLETED ON
1 Developing Container Yard with Road at our CFS site, Ponnery High Road, Chennai – 600120 – Sical Distriparks Limited, Chennai (AREA = 18587 SQM) 1052.22 Feb.2007
2 Developing Container Yard and Road at our CFS site, in Tuticorin – Sical Distriparks Limited, Tuticorin 353.52 Mar.2008
3 Developing Container Yard with Road at our CFS site, Ponnery High Road, Chennai – 600120 – Sical Distriparks Limited, Chennai 629.98 Apr-08
4 Construction of two storey Administrative complex, Elevated Ware house, Laden Concrete container yard for 1.5 lakh sq ft, Laden WBM container yard for 1.00 lakhs Sq.ft, Internal Approach road, Open drain, compound wall 9’0” hollow block work and 3’0” height barbed wire fencing, Weigh bridge and operator’s cabin in the New CFS @ Milavittan, Tuticorin (AREA = 23234 SQM) 1624.86 Jun-10
5 Construction of proposed Elevated ware house shed, at survey no.150,151 part,VichurVillage,ponneri taluk,Thiruvalluvar District(42000Sq.ft) 200.53 Jul-11
6 Providing concrete yard for the laden container staking yard- 20000 sq.mtr, Providing concrete yard for the 100 Ton Weigh bridge – 1000 S.Mtr, Repairs to the existing damaged import container yard – 2500 S. Mtr at Sical CFS, Chennai”. 695.94 Apr-12

Start typing and press Enter to search